Lourdes Grotto

Information about the Project

Completion Date: 2022

Location: Rawa Mazowiecka

Decoration Area: 250m2

Investor: Parish of the Immaculate Conception of the Blessed Virgin Mary in Rawa Mazowiecka

Project Description

Construction of an imitation of the Lourdes grotto on the grounds of the Peace Garden. The grotto completely covers the sacristy and toilet building. The highest point of the mainsail is 6.5m.

Scope of Work

The project included construction:

  • Construction of the Lourdes grotto, which supports the structure of the building completely covering it with artificial rock.
  • Construction of a rooftop observation deck with a rock staircase
  • Making a jet on the inner wall of the grotto
  • Building an altar
  • Incorporating pots for climbing plants

The total construction area of artificial rocks is 250m2.